Project Schedule revised by pmg on 11/03/05

  • Week of Oct 24: Project Kick-off Meeting to discuss site outline and functions for the district and for each of the schools
  • Week of Oct 31: develop designs, produce graphics, port existing content
  • Week of Nov 7: second meeting to discuss design for District Site and example school site.
  • Week of Nov 28: SMC personnel edit final content for site
  • Week of Dec 5: District site beta-1 (private); training/support
  • Week of Dec 12: District site go live, on-going training/support, intro to school personnel
  • Week of Jan 2: Present & Discuss with school personnel
  • Week of Jan 9: Present School sites design direction
  • Week of Jan 16: School sites beta-1 (private); training/support
  • Week of Jan 23: School sites beta-2 (public); training/support
  • Week of Jan 30: School sites go live, on-going training/support
« November 2008 »
Su Mo Tu We Th Fr Sa
1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30
 

This site conforms to the following standards:

  • Section 508
  • Valid XHTML
  • Valid CSS